After waiting years for an off-plan home to complete, it is tempting to sign the handover papers and start moving in. But the inspection you do before accepting the keys, known as snagging, is your best chance to get defects fixed quickly and at the developer's cost. Developers generally respond faster to issues logged at handover than to complaints months later. Here is how to approach snagging in Dubai and what to check.
What snagging means
A snag is any defect or unfinished item: a cracked tile, a door that does not close, poor paintwork, a leaking tap or an air-conditioning unit that does not cool properly. Snagging is the process of identifying these items, recording them and agreeing with the developer that they will be fixed. Most new homes have snags; the goal is not perfection but to make sure everything is put right.
When snagging happens
Developers typically send a handover notice once the building completion certificate is issued. The process usually involves:
- Settling the handover payment and fees, or confirming mortgage arrangements.
- Booking an inspection appointment.
- Inspecting the unit and submitting a snag list.
- The developer rectifying the items, followed by a re-inspection.
- Signing the handover documents and receiving keys.
Some developers allow inspection before final payment, others after. Clarify the sequence and do not sign a statement accepting the unit as defect-free if it is not.
Bring the right tools
- Your floor plan and the specification sheet from the sales agreement
- Masking tape to mark defects
- A phone or plug-in tester for every socket
- A torch, spirit level and tape measure
- Your phone camera for timestamped photos
Room-by-room checklist
Walls, ceilings and floors
- Paint finish: patches, drips, uneven colour or marks
- Cracks in plaster or around door frames
- Tiles: chips, hollow sounds when tapped, uneven grout or lippage
- Wooden floors: gaps, scratches or boards that move
- Skirting boards firmly fixed and sealed
Doors and windows
- Every door opens, closes and locks smoothly
- Gaps around frames and seals on balcony doors
- Windows lock properly and have no cracks or scratches
- Sliding doors run smoothly and close fully, important for dust and heat
Kitchen
- Cabinet doors aligned, hinges and drawers working
- Worktops undamaged and sealed at joins and around the sink
- Appliances, if supplied, switch on and function
- No leaks under the sink after running water for several minutes
- Extractor hood working and vented
Bathrooms
- Water pressure and hot water at every outlet
- Drainage: showers and basins empty quickly with no smell
- Silicone sealing around baths, showers and basins complete
- Toilets flush properly and do not run continuously
- Floor falls towards the drain, with no pooling water
- Extractor fans working
Electrical
- Test every socket and switch
- All lights working, fittings secure
- Distribution board labelled clearly
- Intercom, doorbell and smoke detectors functioning
Air-conditioning
- Every unit cools effectively; let it run for a while
- Thermostats respond correctly
- No water dripping from units or vents
- Noise levels reasonable, especially in bedrooms
Balconies and outdoor areas
- Railings and glass balustrades secure and undamaged
- Drainage outlets clear
- For villas and townhouses: garden levels, irrigation, roof access and external paint
Specification check
Compare what you see with what you were promised: flooring type, kitchen brand, built-in wardrobes, and room sizes within reasonable tolerance. Raise any discrepancy formally.
Recording and submitting snags
Make a numbered list with photos, location and a short description. Submit it through the developer's official channel and keep a copy. Ask for a timeline for rectification and a re-inspection date. Avoid moving furniture in before major snags are fixed, as it can make repairs harder and lead to disputes over who caused damage.
Should you hire a professional snagging company?
Professional inspectors use moisture meters, thermal cameras and experience of common issues in Dubai builds. Fees vary with property size. For larger units, villas and anyone buying from overseas, a professional report is often worth the cost. They may identify issues an untrained eye would miss, such as hidden leaks or poor waterproofing.
After handover: defect liability
UAE law and most sales agreements provide a period during which the developer remains responsible for certain defects. Commonly, there is a defect liability period of around one year for general items after completion, and longer liability for major structural elements under the UAE Civil Code. Check your contract for the exact terms, and report any new issue promptly and in writing.
Common mistakes
- Rushing the inspection in a single short visit
- Signing that the unit is accepted without listing snags
- Not testing air-conditioning properly in cooler months
- Failing to follow up in writing
Snagging a ready resale property
Snagging is usually associated with new builds, but a similar inspection is worth doing when buying a resale home. You will not have a developer to fix items, so use your findings to negotiate the price or ask the seller to repair key issues before transfer, written into Form F. Pay particular attention to air-conditioning, water heaters, bathroom waterproofing and signs of past leaks, which are among the costlier items to put right.
Moving in after snagging
Once major snags are resolved and the keys are handed over, register your DEWA and cooling accounts, apply for move-in permits through building management and book a slot for the service lift. Keep your snag list and the developer's sign-off with your property documents. If items remain open, agree a written timeline and keep following up.
Get handover-ready with Modac Real Estate
Modac Real Estate supports off-plan buyers through completion, from coordinating snagging inspections to arranging tenants once the keys are in hand. Explore off-plan projects, learn about our property management service, or talk to a Modac advisor about your upcoming handover.